'''REPORT ON THE STATUS OF MILESTONES IN SUBMISSION/APPROVAL/DEDICATION PROCESS''' | '''REPORT ON THE STATUS OF MILESTONES IN SUBMISSION/APPROVAL/DEDICATION PROCESS''' | ||
'''Last updated: | '''Last updated: 15 November 2013''' | ||
This ongoing report shows the status of Milestones in the various stages of the process, updated continually by IEEE History Center staff. Milestones are listed with their docket numbers. The IEEE Region and the sponsoring organizational unit are shown in parentheses. ''Please note the titles given here are shortened or working titles, '''not''' the full or official titles. ''While in the approval process, proposals have a History Committee advocate assigned to them, whose initials are given in brackets. Proposals in progress can be viewed on the IEEE Global History Network at: [http://www.ieeeghn.org/wiki/index.php?title=Special%3AAllpages&from=&namespace=104 http://www.ieeeghn.org/wiki/index.php?title=Special%3AAllpages&from=&namespace=104] ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ | This ongoing report shows the status of Milestones in the various stages of the process, updated continually by IEEE History Center staff. Milestones are listed with their docket numbers. The IEEE Region and the sponsoring organizational unit are shown in parentheses. ''Please note the titles given here are shortened or working titles, '''not''' the full or official titles. ''While in the approval process, proposals have a History Committee advocate assigned to them, whose initials are given in brackets. Proposals in progress can be viewed on the IEEE Global History Network at: [http://www.ieeeghn.org/wiki/index.php?title=Special%3AAllpages&from=&namespace=104 http://www.ieeeghn.org/wiki/index.php?title=Special%3AAllpages&from=&namespace=104] ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++ |
Revision as of 19:25, 15 November 2013
REPORT ON THE STATUS OF MILESTONES IN SUBMISSION/APPROVAL/DEDICATION PROCESS
Last updated: 15 November 2013
This ongoing report shows the status of Milestones in the various stages of the process, updated continually by IEEE History Center staff. Milestones are listed with their docket numbers. The IEEE Region and the sponsoring organizational unit are shown in parentheses. Please note the titles given here are shortened or working titles, not the full or official titles. While in the approval process, proposals have a History Committee advocate assigned to them, whose initials are given in brackets. Proposals in progress can be viewed on the IEEE Global History Network at: http://www.ieeeghn.org/wiki/index.php?title=Special%3AAllpages&from=&namespace=104 ++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++
Total dedicated milestones: 133, dedicated special citations: 1
Total Approved milestones: 134, approved special citations: 1
A. ADVOCATES NEEDED FOR THE FOLLOWING MILESTONES:
2013-20 CRC102-A Activation 1954 (Region 8, Italy Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:CRC102-A_activated_at_Politecnico_di_Milano_by_Luigi_Dadda
2013-24 ASCII (Region 2, New Jersey Coast Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:ASCII_MIlestone_-_IEEE_NJ_Coast_Section
2103-26 Hertz Generation of Electromagnetic Waves (Region 8, Germany Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:First_generation_and_experimental_proof_of_electromagnetic_waves_1886-1888.
2013-27 Invention of Stereo (Region 8, UKRI Section)
http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Improvements_in_and_relating_to_Sound-transmission,_Sound-recording_and_Sound-reproduction_systems_by_Alan_Dower_Blumlein
2013-29 Middle and Upper Atmosphere Radar (Region 10, Kansai Section)http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:The_MU_%28Middle_and_Upper_atmosphere%29_radar%2C_1984
B. STATUS
B.1 Proposals Being Written on the GHN and Awaiting Submission
2013-12 Bayer Color Filter Array [DBu] http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Color_Filter_Array
2013-13 Erbium-Doped Fiber Optical Amplifier [MS] (Region 8, UKRI Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Development_of_the_Erbium-Doped_Optical_Fiber_Amplifier
2013-15 Interactive Video Games [AM] (Region 1, New Hampshire Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Interactive_Video_Games
2013-19 Virginia Smith HVDC Converter [GC] (Region 5, Denver Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Virginia_Smith_HVDC_Converter_Station_with_Integrated_AC_Voltage_Control_Function
2013-20 CRC102-A Activation 1954 (Region 8, Italy Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:CRC102-A_activated_at_Politecnico_di_Milano_by_Luigi_Dadda
2013-24 ASCII (Region 2, New Jersey Coast Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:ASCII_MIlestone_-_IEEE_NJ_Coast_Section
2013-25 TPC-1 Transpacific Cable (Region 10) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:TPC-1_System
2013-27 Invention of Stereo (Region 8, UKRI Section)
http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Improvements_in_and_relating_to_Sound-transmission,_Sound-recording_and_Sound-reproduction_systems_by_Alan_Dower_Blumlein
B.2. Proposals Submitted Awaiting Advocate Approval
2013-06 SPARC RISC Architecture [FA-H] (Region 6, Santa Clara Valley Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:SPARC_RISC_Architecture_Introduction,_1987
2013-07 Cruft High Tension Laboratory [JCM] (Region 1, Boston Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Cruft_HighTension_Laboratory,_Harvard_School_of_Engineering_and_Applied_Science
2013-09 Mark 1 Automatic Sequence Controlled Calculator [LF] (Region 1, Boston Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Mark_1_Automatic_Sequence_Controlled_Calculator_(ASCC)_by_Howard_Aiken_and_IBM
2013-16 First RISC Mircoprocessor [FA-H] (Region 6, Oakland East Bay Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:First_RISC_Microprocessor
2013-18 Vapor-phase Axial Deposition [DBu] (Region 10, Tokyo Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Invention_and_development_of_vapor-phase_axial_deposition_(VAD)_method_for_mass_production_of_high-quality_optical_fiber_for_telecommunication
2013-22 Introduction of Apple II Computer [EJ] (Region 6, Santa Clara Valley Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Introduction_of_the_Apple_II_Computer:_1977-1978
2103-26 Hertz Generation of Electromagnetic Waves (Region 8, Germany Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:First_generation_and_experimental_proof_of_electromagnetic_waves_1886-1888.
2013-29 Middle and Upper Atmosphere Radar (Region 10, Kansai Section)http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:The_MU_%28Middle_and_Upper_atmosphere%29_radar%2C_1984
B.3. Proposals Approved by Advocates and Awaiting Finalized Citations Approval from Proposers
2013-03 First Breaking of Enigma Code by Polish Cipher Bureau [IE] (Region 8) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:The_First_Breaking_of_Enigma_Code_by_the_Team_of_Polish_Cipher_Bureau%2C_1932-39
2013-28 Apple I Computer [EJ] (Region 6, Santa Clara Valley Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Introduction_of_the_Apple_I_Computer:_1976
B.4. Proposals Ready for History Committee Action
2012-05 Bell Laboratories Inc., The First 60 Years [DM] (Region 1, North New Jersey Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Bell_Telephone_Laboratories%2C_Inc.%2C_the_First_60_Years%2C_1925-1984
B.5.1 Proposals Approved By History Committee Ready for Board of Directors Action
2012-06 High Temperature Superconductivity [GC] (Region 5, Houston Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:High_Temperature_Superconductivity
2013-10 20-inch Diameter Photomultiplier Tubes [SMiz] (Region 10, Nagoya Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:The_20_inch_Diameter_Photomultiplier_Tubes
2013-11 Ampex Videorecorder [LL] (Region 6) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Ampex_Videotape_Recorder_-_1956
2013-14 Battery Industries in Japan [HK] (Region 10, Kansai Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Birth_and_Growth_of_Primary_and_Secondary_Battery_Industries_in_Japan
2013-17 Rheinfelden Hydroelectric Power Plant [JCM] (Region 8, Germany Section, PES) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Rheinfelden_Hydroelectric_Power_Plant,_1898_-_2010
2013-21 First Blind Flight [MS] (Region 1, Long Island Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:First_Blind_Flight%3A_A_Joint_IEEE-AIAA_Milestone_Proposal
2013-23 PC Operating System 1974 [TB] (Region 6, Santa Clara Valley Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:BIRTH_OF_THE_PC_OPERATING_SYSTEM_1974
2013-08 Birthplace of Silicon Valley [TB] (Region 6, Santa Clara Valley Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:The_Birthplace_of_Silicon_Valley
B.5.2 Proposals Submitted to Board of Directors for Action
2012-07 Line Spectrum Pair Technology for Speech Coding [MB] (Region 10, Tokyo Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Line_spectrum_pair_(LSP),_an_essential_technology_for_high-compression_speech_coding,_1975
2013-01 Gapless Metal Oxide Surge Arrester [DB] (Region 10, Tokyo Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Gapless_Metal_Oxide_Surge_Arrester_(MOSA)_for_electric_power_systems,1975
2013-02 Unidirectional Microphone [APY] (Region 4, Chicago Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Unidirectional_Microphone
2013-04 Sharp Thin-Film Transistor LCD [HK] (Region 10, Kansai Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:Sharp_14-inch_thin-film-transistor_liquid-crystal_display_%28TFT-LCD%29_for_TV%2C_which_has_ushered_in_TFT_LCD_industry
2013-05 (Region 7, Vancouver Section) [DBar] First Digitally Processed SAR Image http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:First_Digitally_Processed_Image_from_a_Spaceborne_Synthetic_Aperture_Radar
B.6. Dedications Scheduled or Being Planned, all Approvals Having Been Received
2012-04 First AIEE Technical Meeting (Region 2, Philadelphia Section) 15 December 2013 http://www.ieeeghn.org/wiki/index.php/Milestone-Proposal:First_Technical_Meeting_of_AIEE_1884
B.7 DEDICATIONS HELD THIS YEAR
2011-07 Pioneering Laptop Computer (Region 10, Tokyo Section), Dedication: 29 October 2013 www.ieeeghn.org/wiki/index.php/Milestone-Nomination:Toshiba_T1100%2C_a_pioneering_contribution_to_the_development_of_laptop_PC%2C_1985
2012-02 Invention of Holography, 12 June 2013 (Region 8, UKRI Section) http://www.ieeeghn.org/wiki/index.php/Milestones:Invention_of_Holography <span id="fck_dom_range_temp_1373981674640_225" />
2012-03 Krka-Sibenik Power System (Region 8, Croatia Section) Dedication: 5 July 2013 http://www.ieeeghn.org/wiki/index.php/Milestones:Krka-%C5%A0ibenik_Electric_Power_System,_1895
B.8. DEDICATIONS HELD IN 2012 (For a list of all Milestones dedicated, see List of Dedicated Milestones )
2010-04 Field Effect Electron Microscope, 31 January 2012 (R10 -- Tokyo)
2010-03 G3 Facsimile, 5 April 2012 (R10 – Tokyo Section)
2011-09 Low Loss Optical Fiber, 1 May 2012 (R1 -- Photonics Society)
2011-02 B&O Railroad electrification 21 June 2012 (R2 – Baltimore Section)
2010-10 LORAN, 27 June 2012 (R1 – Boston Section)
2010-11 Whirlwind Computer 27 June 2012 (R1 – Boston Section)
2011-04 SAGE system, 27 June 2012 (R1 – Boston Section)
2009-09 First Reliable HV Fuse, 3 August 2012 (R4 – Chicago Section)
2011-08 Floating Gate EEPROM, 21 August 2012 (R6, Santa Clara Valley Section)
2009-05 Bose experiments in radio, 15 September 2012 (R10 – Central India)
2009-04 Raman Effect, 15 September 2012 (R10 – Central India Section)
2009-06 Bar Code, 22 October 2012 (R2 Philadelphia Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Nomination:Birthplace_of_the_Bar_Code,_1948
2012-01 First Optical Fiber Laser and Amplifier, 26 October 2012, Photonics Society http://www.ieeeghn.org/wiki/index.php/Milestone-Nomination:First_Optical_Fiber_Laser_and_Amplifier
2011-05 Rincon del Bonete [LF] (R9 – Uruguay Section) http://www.ieeeghn.org/wiki/index.php/Milestone-Nomination:Rincon_del_Bonete_Hydroelectric_Plant_and_Transmission_System
B.9. DEDICATIONS HELD DURING THE PREVIOUS YEAR
2009-07 Eel River HVDC Converter (R7) 24 February 2011
2009-12 Mercury Spacecraft controls 24 February 2011 (R5)
2010-01 SPICE Circuit Simulation Program 20 February 2011 (R6)
2010-05 Discovery of Superconductivity 8 April 2011 (R8)
2008-18 Marconi’s First Wireless Experiments, 29 April 2011 (R8)
2010-06 Pearl Street Station, 10 May 2011 (R1)
2010-08 Lunar Module 20 July 2011 (R1)
2009-13 First Satellite Broadcast to the Public, 18 November 2011 (R10 – Tokyo Section)
2010-09 Real-Time Packet Switching 8 December 2011 (R1 – Sig Proc Soc.)
2010-02 Apollo Guidance Computer 13 December 2011 (R1 Boston Section)
C. POTENTIAL MILESTONES BEING RESEARCHED OR EXPLORED
(that History Center staff are aware of)
High performance Perpendicular Magnetic Recording, 1977
Cellular radio
First All-Electronic Television Broadcasts (BBC)
London to Adelaide telegraph line
Weston meters
Charles Kao optical fiber (R8 UKRI Section)
John Logie Baird television (R8 UKRI Section)
Harrisons clock (R8 UKRI Section)
Photovoltaic effect (R8 – France)
RCA Victor (R2 Philadelphia Section)
386 Micro (Region 6, Santa Clara Valley Section)
4004 Micro (Region 6, Santa Clara Valley Section)
Canadian Niagara Plant (Region 7)
Oberlin-Smith electromagnetic recording (Region 2, South Jersey Section) (possible ASME codesignation?)
D. OTHER MILESTONES ACTIVITY