Rincon del Bonete Hydroelectric Plant and Transmission System

In December, 1945, sorely needed Hydroelectricity started flowing from here into the country.
World War II had interrupted the work of the German consortium led by Siemens. But a motivated team of Uruguayan engineers reformulated and completed the project using American-supplied equipment.
The large artificial lake spurred further Rio Negro electrification; availability of abundant, clean hydroelectricity was a turning point in Uruguay's development and quality of life.






Please also include references and full citations, and include supporting material in an electronic format (GIF, JPEG, PNG, PDF, DOC) which can be made available on the IEEE History Center’s Web site to historians, scholars, students, and interested members of the public. All supporting materials must be in English, or if not in English, accompanied by an English translation. If you are including images or photographs as part of the supporting material, it is necessary that you list the copyright owner.

In the space below the line, please describe the historic significance of this work: its importance to the evolution of electrical and computer engineering and science and its importance to regional/national/international development.






What features or characteristics set this work apart from similar achievements?

As the German contractor could not complete the work, Uruguayan engineers decided to study the project and take charge of its reformulation employing electromechanical equipment manufactured in the USA.
The challenge (w/o precedents) required deep study, a lot of dedication, a dose of ingenuity and application of sound engineering principles.
The project culminated with the mounting and commissioning of the imported equipment made entirely by Uruguayan engineers and technicians trained by them.
All this was made during difficult war times. The successful completion marked a very high point in the history of engineering in Uruguay.

The big artificial lake (1070 Square Km) was at that time the largest in LatinAmerica, and its capacity allows the generation of Power for 4 months, even during a drought.

Rincon del Bonete set an example as the country turned to clean renewable Hydropower, replacing burning of costly coal imports.
It set the stage for the industrial development, and the development of the electric Transmission System allowed hydroelectric energy for rural electrification and welfare of the whole population of the country.

Please attach a letter in English, or with English translation, from the site owner giving permission to place IEEE milestone plaque on the property.

The letter is necessary in order to process your nomination form. Click the Attachments tab to upload your letter.

Approval spanish.jpg